Friday, April 4, 2014

Main St Bridge Update 4/4/14 - NOTE SATURDAY CONSTRUCTION!

 
 
 
The first full week of construction is coming to an end, and here is today's update from Main Street Initiative President John Moriarty:
 
According to Paul’s [Moynihan] morning update, the general work for today is:
 
n  Demolition of sidewalks within construction zone is primary work item
 
But, please take note of this poignant item:
 
Contractor (R. M. Piper) crew will work Saturday (4/5) from 7:00 a.m. till 3:00 p.m. inside barriers of work zone
 
It appears there shouldn’t be any impact on Saturday traffic flow or pattern.  If anything think of this as an opportunity for more customers.  Construction workers will occupy parking spaces normally available on Saturday however.
 
John Moriarty, president
Main Street Initiative of Laconia
voice, cell, text 603.455.2084
 
Remember, you can get connected to the Main Street Initiative on both Facebook  and Twitter, or email us to be added to the mailing list. Let us know if you have questions or concerns!

No comments:

Post a Comment

For even more news....

You can like us on Facebook! http://facebook.com/laconiamainstreet