Congratulations are in order! The wonderful Colonial Theatre building is 101 years old today! Come and celebrate under the marquee in beautiful Downtown Laconia with the Laconia Historic Society and others Sunday April 13th from noon to 2pm. Share visions and memories - and Happy Birthday, Dear Colonial!
Sunday, April 13, 2014
Friday, April 4, 2014
Main St Bridge Update 4/4/14 - NOTE SATURDAY CONSTRUCTION!
The first full week of construction is coming to an end, and here is today's update from Main Street Initiative President John Moriarty:
According to Paul’s [Moynihan] morning update, the general work for today is:
n Demolition of sidewalks within construction zone is primary work item
But, please take note of this poignant item:
n Contractor (R. M. Piper) crew will work Saturday (4/5) from 7:00 a.m. till 3:00 p.m. inside barriers of work zone
It appears there shouldn’t be any impact on Saturday traffic flow or pattern. If anything think of this as an opportunity for more customers. Construction workers will occupy parking spaces normally available on Saturday however.
John Moriarty, president
Main Street Initiative of Laconia
voice, cell, text 603.455.2084
Wednesday, April 2, 2014
Main St. Bridge Update 4/2/2014
The latest news; there will be more later from Main Street Initiative President John Moriarty.
Hi All – Update this a.m. (Wednesday 4/2),
n Construction Progress Meeting # 1 at City Hall today at 8:00 a.m. – Room 200-A
If you have questions or concerns, please call. -- Paul
Tuesday, April 1, 2014
Main Street Bridge Update 4/1/2014
![]() |
| You can get a close up view from the pedestrian walkway between Main St. and Beacon St. East, or a bird's eye view from the second floor of the parking garage. |
From Main Street Initiative President John Moriarty:
We are well into day two of the Beacon Street East detour and traffic appears to be moving fairly well. The small exception has been when traffic slows down because of genuine interest in seeing the progress being made. If you find yourself falling into the category of person who finds big construction projects fascinating, please take a look at our Facebook page to see Melissa’s pictures and updates.
There will be a presentation tomorrow morning at City Hall by the project team, at 8:00 a.m. in room 200 A.
As always, please forward questions to Paul, or drop me a line and I will see that they get to him. As I am writing this, I am collating a short list to send to him. I will post them and the answers as they are confirmed.
Enjoy Spring, and Paul’s update below.
Hi All – Update this a.m. (Tuesday 4/1),
n Bridge work will essentially be confined to the Beacon St. East construction area
If you have questions or concerns, please call. Thanks, -- Paul
Friday, March 28, 2014
Main Street Bridge Update 3/28/2014
Did you know that you can follow the bridge project on Facebook, and also receive real-time posts on Twitter?
Today’s update from Paul reads like a good end to the first week of activity.
Hi All, -- Update this a.m. (Friday 3/28),
n Work around the site will be light today
n Traffic on Beacon St. East and Beacon St. West will flow freely thru the day
n Closure of Beacon St. East and Phase 1 Detour will begin Monday a.m. March 31st – Details available on City Website – Main St. Bridge
If you have questions or concerns, please call. – thanks, Paul
As always, you can email, call or text with questions or comments, or even if grab a cool pic of the construction while it happens!
John Moriarty, president
Main street Initiative of Laconia
Cell / text 603.455.2084
Email: john@mymoriarty.net
Main Street Bridge Update 3/27/2014
In addition to forwarding the messages from the City, we at Main Street are here to collect your questions and concerns and pose them anonymously to the City. We will then post the questions and answers here so that in the likely event that others have the same question, it will save time and effort for all concerned.
Such was the case Tuesday. We forwarded a question posed to us to the City and had an answer the same day.
Q. “April 1st is the start of fishing season, and myself and scores of other anglers enjoy dropping a line off the Main Street Bridge. Will be able to do so this April 1st, and what about April 1st 2015”?
A. “We welcome and encourage anglers to take advantage of the salmon season in areas along the banks of the Winnipesaukee River that are not closed-off as part of the active Bridge Construction Zone. In the immediate Main St. vicinity, the Beacon Street West bridge section, the Mill St. Pedestrian Bridge, Rotary Park, Stewart Park, the area behind the Landmark Inn (and Walgreens) and the Beacon St. West Riverwalk are all fully available to the public.
In the 2015 cycle, the only difference should be that Beacon St. West would be closed because of active bridge construction, but, at that time, Beacon St. East should be fully available”.
--thanks to Paul Moynihan for that answer.
Director of Public Works, Paul Moynihan has one important announcement and the daily update to share:
NOTE: R.M. Piper (Contractor) has confirmed that the Phase 1 Detour will be put into effect on Monday, March 31st during the morning hours.
Hi All, -- Update this a.m. (Thursday 3/27),
n Traffic Island at mouth of Beacon St. East (edge of Phase 1 work area) will be removed today
n Site Prep work will continue on sidewalk area at the south end of the Parking Garage and with staging set-up under the bridge on the Beacon St. east side
n Crosswalk striping around the work area will be enhanced
n Traffic on Beacon St. East and Beacon St. West will flow freely thru the day with only periodic delays on the Beacon St. East side
Thanks for tuning in.
Yours truly,
John Moriarty, president
Main Street Initiative of Laconia
Main Street Bridge Update 3/26/2014
From Laconia Main Street Initiative President John Moriarty:
Good morning everyone – I am sorry this is so late.
I for one really appreciate the superb communication from Paul Moynihan regarding the bridge re-decking project.
Here is Paul’s update for today.
John Moriarty, president
Main Street Initiative of Laconia
Hi All, --Update this a.m. (Wednesday 3/26),
n Beacon St. East wing will have minor lane-narrowing (with cones) while staging is set-up under the bridge
n R.M. Piper will continue removing items on the sidewalk area at the south end of the Parking Garage
n Time permitting, Piper will remove the easterly Traffic Island that is located in the Phase 1 work area
n Traffic on Beacon St. East and Beacon St. West will flow freely thru the day